Transmission Company of Nigeria Announces Two-Week Power Outage

Transmission Company of Nigeria (TCN) has announced a 14-day power outage in its Amukpe substation, effective immediately. CONTINUE READING

This information was disclosed in a press release issued on Saturday by TCN’s General Manager, Public Affairs, Ndidi Mbah.

Mbah said the disruption would begin on May 4 and last till May 17. This means some communities in Edo State and Delta would be in blackout during the duration of the outage.

The outage, according to the TCN, is to enable contractors to have a safe environment to erect two 132KV transmission towers at the substation.

The company also said that as a result of the intended power outage, there would be no bulk power supply to Benin DisCo through the Adeje industrial, woodland, Mosogar, Sapele and Abraka feeders for the period.

“The Transmission Company of Nigeria (TCN), hereby states that it will commence the erection of two number 132kV transmission towers at its Amukpe Transmission Substation.

”And will equally restring a portion of the Benin-Delta and Delta-Oghara 132kV double circuit transmission lines from Saturday, May 4 to May 17, 2024.

“Consequently, Amukpe Substation will be out of power for the duration of the work.”